Cambridge IGCSE 0450 · Topic 7 of 10

Operations management

Operations turn inputs into goods and services efficiently. This covers production methods, productivity, technology, costs and break-even, quality and location decisions.

📌 Key points

  1. Production turns inputs into outputs; productivity = output ÷ inputs (e.g. output per worker). It can be raised by training, better technology, motivation and better methods.
  2. Job production makes one-off items to order; batch production makes groups of identical products; flow production makes large numbers continuously on a production line.
  3. Lean production cuts waste: just-in-time keeps almost no inventory, with supplies arriving just when needed; kaizen is continuous improvement through small changes.
  4. Technology such as automation, CAD (computer-aided design), CAM (computer-aided manufacturing) and EPOS improves productivity and accuracy but costs a lot and may cause job losses.
  5. Fixed costs do not change with output; variable costs change directly with output. Total cost = fixed costs + variable costs; average cost = total cost ÷ output.
  6. Economies of scale lower average costs as a business grows (purchasing, marketing, financial, managerial, technical); diseconomies of scale raise them (poor communication, low morale, slow decisions).
  7. Break-even is where total revenue = total costs. Break-even output = fixed costs ÷ contribution per unit, where contribution = price − variable cost per unit.
  8. Margin of safety = actual sales − break-even output. A break-even chart helps plan, but assumes all output is sold at one price.
  9. Quality control checks finished products; quality assurance checks quality at every stage of production; total quality management (TQM) makes every employee responsible for quality.
  10. Location depends on: market, raw materials, labour, transport, power, government grants and rules; shops need to be where many customers pass by.

📖 Key terms

Productivity
A measure of how efficiently inputs are turned into outputs, e.g. output per worker.
Batch production
Producing a limited number of identical products, then switching to a different batch.
Flow production
Producing large quantities of a standardised product on a continuous production line.
Just-in-time
A lean method in which supplies arrive exactly when needed, so almost no inventory is held.
Break-even point
The level of output at which total revenue equals total costs.
Contribution
Selling price minus variable cost per unit.
Margin of safety
The amount by which sales exceed the break-even level of output.
Total quality management
Making quality the responsibility of every employee at every stage.

✏️ Worked example

A firm has fixed costs of $12,000 a month. It sells its product for $20 and the variable cost per unit is $14. It sells 2,600 units a month. Calculate the break-even output, margin of safety and profit.

  1. Contribution per unit = $20 − $14 = $6.
  2. Break-even output = fixed costs ÷ contribution = $12,000 ÷ $6 = 2,000 units.
  3. Margin of safety = 2,600 − 2,000 = 600 units.
  4. Profit = margin of safety × contribution = 600 × $6 = $3,600.
  5. Answer: break-even 2,000 units; margin of safety 600 units; profit $3,600.
💡 Exam tip

Break-even output is a number of units, not dollars. Check by testing: at break-even, total revenue and total cost should be equal.

Test yourself8 questions from a bank of 17. A new mix every time.
Start the quiz →

It’s bedtime! 😴

It’s late, and even Numo is getting sleepy. The best thing you can do for your learning now is… go to sleep!

✨ Sleep helps you

  • 🧠 remember what you learned today: your brain saves it while you sleep
  • 🌱 grow and stay healthy
  • ⚡ wake up with energy, ready to learn and play
  • 😊 feel happy and calm

🦉 Going to bed late can make you

  • 😩 tired and sleepy at school tomorrow
  • 🤯 find it harder to focus and to remember
  • 😠 grumpy and easily upset
  • 🤧 catch colds more easily

Children your age need 9 to 12 hours of sleep every night. Numo will be right here tomorrow!